General Description Manual PO
Manual PO's (manual planned orders) override Calc PO's.
Resource Planning will only begin calculating planned orders in the week
following the last Manual PO.
Manual PO's can be inserted for 0 (zero) value.
After keying the Manual Po values click on the button
To remove a Manual PO delete any numbers from the field.
StepTechnical Description Manual PO
1.See the calculated planned orders below :
2.
3If you do not want any planned orders to be released until 10-13-06 ,
3a.and then you only want to order 100 on 10-13-06 ,
3bkey 100 on the Manual PO line in that week and click Update Item.
3bThe result will be as shown below.
4.