| General Description Calc PO |
| Calc PO (Calculated Planned Orders) show the calculated replenishment week by week into the future. |
| They take into account : On Hand , Needs , Inbound , and prior Calc PO |
| Calc PO show in the On Hand in the week they will arrive. |
| Step | Technical Discussion of Calc PO |
| 1. | Calc PO shows from Past Due out 208 weeks into the future. |
|  |
| 2. | On Hand Nov 7, 2006 = 14 |
| 3. | Calc PO =Nov 6, 2006 = 20 |
| 4. | Lead Time = 4 weeks |
| 5. | Needs from Nov 8 , 2006 through Dec 5, 2006 = 10 |
| 6. | On Hand Dec 5, 2006 = 24 |
| 7. | 14 On hand + 20 Calc PO - Needs 10 = On Hand 24 |